A warm engine needs a price tag.
Energy Trust seeks a roughly $60,000 study of large generator block heaters. Questions are due November 12; missing the intent date does not bar a proposal.

Backup generators must start when ordinary power fails. Keeping their engines warm takes energy of its own. Energy Trust wants researchers to establish what conventional block heaters cost to buy and install, especially at nine kilowatts and above. Its current incentive rules stop at 8.9 kilowatts because the larger equipment lacks reliable baseline cost data.
The work combines installer interviews, a manufacturer interview and a final report. Researchers need a credible sampling and recruitment plan, clear cost comparisons and an example of a similar past report. The anticipated budget is about $60,000 under a negotiated spending cap; justified higher proposals will be considered, with lower-cost alternatives explained.
The call opened October 30. Email questions and an expression of interest by November 12, then submit the PDF proposal by December 1 at 5 p.m. Pacific. The request expressly allows proposals without an earlier expression of interest. Disclose planned AI use and explain how project data will be protected.
Before you start
Research teams able to design interviews, recruit Oregon installers, analyze equipment and labor costs, and provide a similar past report. Staff resumes, insurance information, conflict disclosure, signed representations, diversity responses and data safeguards are required. No minimum business age or ownership certification is stated.
The finer details
November 12 is the contact date; no cutoff time is published. Firms may submit proposals without submitting intent. Use an all-day reminder for questions or an expression of interest. Final proposals must be received by 5 p.m. Pacific on December 1, with the signed transmittal letter and required appendices.
Research concerns installers across Oregon; no Oregon headquarters requirement stated.
Research target: Cost estimates for electric resistance thermosiphon block heaters 9 kW and larger; proposed sampling should target 15% precision at 90% confidence.
Certification: No minimum subcontract share is required. Directing at least 15% of contract value to qualifying firms may earn up to a 5% scoring bonus. Confirm uncertain certifications with the project manager.
AI and data: Disclose tools and planned uses. The attached AI policy requires protected Energy Trust data to remain in US storage/processing and outside model training.
The request gives two different final-report revision periods, two weeks and three weeks; confirm the delivery schedule before pricing.
Official sources checked 3 November 2026; detailed scope is recorded with the saved evidence.